CCRC 1314-020 D & C Floodways & Road Repairs Various Locations

The project was commissioned by the Cassowary Coast Regional Council Far North Queensland.

Works included but were not limited to Floodway Design in accordance with the Department of Transport & Main Roads Drainage Specifications Floodway Protection. Construction of upstream and downstream concrete batter protection sealing, pavement, widening and reconstruction works involving cement modified base and cement stabilization. Reform table drain and line with rock filled wire baskets. Environmental factors. Install depth markers, removal of debris, replacement of guardrails and guideposts.

Construction Period: August 2014 to December 2014
Final Construction Period: August 2014 to February 2015
EOT approved – no liquidated damages applied

Outcome

  • More than 1000m2 of gabion wire mattress installed in various sections
  • Applications of various pavement treatment types such as plant mixed cement modified base, cement stabilization, unbound (various types), Insitu stabilization
  • Enhanced flood immunity to all works
  • Culvert upgrade and installation

Details & Contact

Duration: August 2014 – February 2015
Client: Cassowary Coast Regional Council
Contact: David Trotter
Phone: 07 4030 2275
Value: Award: $1,18,566.00 | Final: $1,512,398.70