Illich Park Precinct Upgrade

April Update

Activities:

Site Demolition – 100% complete

  • Remove existing goal posts and footings
  • Remove existing bollards
  • Remove existing light towers and footing
  • Remove irrigation
  • Remove electrical
  • Remove 3 x medium sized trees and 3 x large trees

Cut and fill – Using Fortini’s scoop with BMS laser GPS guidance to cut and fill playing fields to level and cut drains, additional fill moved to stockpile.  Approximately 90% complete

GST and fill testing – Regularly conducting MDD and Nuke testing for compaction, 95% fill areas, 85% GST.  Approximately 80% complete

Bulk Haulage – Removing top soil stockpile and additional fill stockpile to Stuart Tip – Approximately 25% complete