TMR – Pend 1619 Mareeba-Dimbulah Road

Road pavement rehabilitation and reconstruction to provide a 9.0m wide bitumen sealed roadway.

Including supply and place 30,000 tonne type 2.2 travel to profile design. Insitu stabilization of 55,000m2 of pavement. Extension of existing culvert as well as installation of new culverts. Reform table drains to design site. Site rehabilitation.

Construction Period: August 2012 to November 2012
Final Construction Period: August 2012 to April 2013
The project was delivered 10 days after PC Date. LD’s applied.

Outcome

  • Pavement reconstruction and widening
  • 6km of pavement overlay
  • 6km of insitu stabilization
  • 26 culvert extensions and replacement
  • 12km of drainage

Details & Contact

Duration: October 2012 – May 2013
Client: Department of Transport & Main Roads
Contact: Mike Tait
Phone: 07 4050 5593
Value: Award: $5,423,280.00 | Final: $6,327,644.97