Whitsunday Regional Council Flood Damage Pavement Repairs

Construction of 4500sqm of pavement with 2.3CMB and two coat seal to Main Road standards.

Construction Period: May 2009 to June 2009
Final Construction Period: May 2009 to July 2009
EOT approved – no liquidated damages applied

Outcome

  • Works to Main Roads Specifications
  • Cement modified gravels
  • 2 coat seal
  • Successful negotiation of 50% additional works with WRC

Details & Contact

Duration: May – June 2009
Client: Whitsunday Regional Council
Contact: Gus Bartlett, Brendan Day Main Roads
Phone: Gus – 0428 725 623
Value: Award: $954,000.00 | Final: $954,000.00